联系方式

  • QQ:99515681
  • 邮箱:99515681@qq.com
  • 工作时间:8:00-23:00
  • 微信:codinghelp

您当前位置:首页 >> CS作业CS作业

日期:2018-05-04 07:04

General Guidelines and schedule for course project:

The course project accounts for 32% of the final grade.

The project should be simulation-based. It offers an opportunity to focus on a specific

subject or technology that are of interest. The course project includes running a system

simulation accompanied by a written report.

1. All students may work individually or in teams of two.

2. Project may be selected from the provided list or proposed by the students. A

minimum of 7 bus system needs to be selected.

3. All material should be submitted electronically by uploading it into the

assignment folder or under the personal Sakai Dropbox.

4. Students may propose their own ideas for this project.

5. The report should be at least 7 pages long.

6. All code files should be uploaded in addition to the report.

Written report guidelines:

The report should follow the following general structure:

1. Title Page: This should be the cover page for the report. It should include the title of

the report, and project team members names

2. Case study/Problem formulation: This section is where details of the related work are

explained. This section can include multiple subsections based on the topic discussed.

Problem formulation, model development, objectives, etc.

3. Detailed solution: mathematical representation of the solution and algorithm flow

diagram, where relent. Simulation results.

4. Conclusions: A very brief overview of the problem being presented/studied.

5. Appendix: detailed code

332:494:01/599:02 --- final project 2

List of suggested projects:

For ONE of the following projects develop an appropriate on-line diagram. Write a

report and a general Matlab M-code, Simulink model or PowerWorld Model.

For ANY of these projects perform the following:

1) Compute the pu one-line model.

2) Compute all bus voltages using any of the methods (Newtown–Raphson or Gauss–

Seidel methods on Matlab or Power World or Simulink)

3) Compute all power values including: power flow on each line (in/out), line losses and

generated power.

Project Option 2.1

The one-line diagram of a power grid is depicted in figure 1. The details for the grid are

given in the figure. Assume a base power of 100MVA and base voltage of 13.2 kV.

Assume the input reactance of the local power grid is 10% based on the transformer T1.

The input resistance of the PV sources is 7% based on their rating and input reactance of

other sources is 7% base on their ratings.

The system data:

Transformer T1: 20 MVA, 33 /13.2 kV, 10% reactance

Transformer T2: 20 MVA, 13.2 / 3.3 kV, 12% reactance

Transformer T3: 5 MVA, 3.3 / 460 V, 6.5% reactance

Transformer T4, T5, and T6: 2 MVA, 3.3 / 460 V, 6.5% reactance

Transformer T7: 5 MVA, 3.3 / 460 V, 6% reactance

Transmission line impedance is given in Table 2

Table 2: Transmission Line Data for project 2.1

Line Resistance (Ω) Series Reactance (Ω)

8–9 .05 0.5

9–10 0.04 0.4

9–11 0.04 0.51

11–12 0.04 0.5

11–13 0.01 0.12

13–14 0.03 0.32

14–15 0.04 0.45

The local loads (bus 16, bus 17 and bus 18) and bus 8 are set at 1 MVA at 0.85 power

factor lagging.

332:494:01/599:02 --- final project 3

Figure 1: System for projects 2.1

332:494:01/599:02 --- final project 4

Project Option 2.2

Figure 2: System for projects 2.2

PV generating station #1: 2MVA; internal impedance 50%

Gas turbine: 1MVA; internal impedance 4%

Transformers: 460V/13.2kV (Y/D) ; 10% internal reactance; 10MVA rated power (all

three phase)

Power grid transformer: 20MVA; 63kV/13.2KV; 7% reactance

B4 load: 1.5MW; pf=0.85 lag

B5 load: 5.5MW; pf=0.9 lag;

B6 load: 4MW; pf=0.95 lag;

B7 load: 5MW; pf=0.95 lag;

B8 load: 1MW; pf=0.9 lag;

332:494:01/599:02 --- final project 5

Transmission Line Data for project 2.2

Resistance: 0.0685 ohm/mile; reactance: 0.4 ohm/mile; half line charging admittance:

11x10-6 siemens/mile

Line 4-7: 5 miles

Line 4-8: 1 miles

Line 5-6: 3 miles

Line 5-7: 2 miles

Line 6-7: 2 miles

Line 6-8: 4 miles

Project Option 2.3

For the single-line diagram in Figure 4 convert all positive-sequence impedance, load,

and voltage data to per unit using the given system base quantities.

Run the power flow program and obtain the bus, line, and transformer input/output

voltages

Figure 4 (a): System for project 2.3

332:494:01/599:02 --- final project 6

Figure 4: System for project 2.3

Project Option 2.4

For the single-line diagram in Figure 5 convert all positive-sequence impedance, load,

and voltage data to per unit using the given system base quantities.

Run the power flow program and obtain the bus, line, and transformer input/output

voltages

(Comment: for L2 please choose a value between 20km to 50 km)

332:494:01/599:02 --- final project 7

Figure 5: System for project 2.4

Project Option 2.5

Propose/choose a power network example with at least 7 buses (either an IEEE test bus,

or other examples from the course textbooks). Provide the system details (i.e. generating

sources, transformers, loads, etc.). Develop the per unit model for the systems. Run the

power flow program and obtain the bus, line, and transformer input/output voltages

(Comment: for L2 please choose a value between 1km to 5km)


版权所有:留学生编程辅导网 2020 All Rights Reserved 联系方式:QQ:99515681 微信:codinghelp 电子信箱:99515681@qq.com
免责声明:本站部分内容从网络整理而来,只供参考!如有版权问题可联系本站删除。 站长地图

python代写
微信客服:codinghelp